Table of contents

Project plan

Each partner organization will be responsible for leading the selected work package. Our project activities are divided according to following planned work packages:

WP1: Project management (Charles University)

 

Kickoff meeting Prague 11/2023
Trans-national project meeting Istanbul 11/2024
Trans-national project meeting Linz 12/2025

 

WP2: Building Pedagogical Pillars and Framework for experience oriented and experiment based STEM-orientation (JYU in close cooperation with CUNI)

Background literature review of real (hands-on) and virtual experiments’ use in STEAM-oriented projects or inquiry

activities.

11/2023-04/2024
Analyzing literature with respect to active learning, creative thinking, real-world applications, fostering digital readiness and

resilience in STEM education

Searching for applicable assessment and evaluation tools

 

WP3: Creation of STEM experiments (JKU)

 

Analysis of available STEAM experiments 01/2024-03/2024
Selection and alterations of one real and one virtual experiment 04/2024
Developing activities incorporating experiments with respect to active learning, creative thinking, real-world applications, fostering digital readiness and resilience 04-05/2024
Reviewing the proposed activities within the team members 06/2024
Testing the activities with pre-service teachers at each partner’s institution 06/2024
Improving the proposed activities 07-08/2024
Adapting existing evaluation tools 08-09/2024

 

WP4: Implementation(BAU)

 

Implementing the activities in pre-service training course(s) 10/2024-01/2025
Implementing the activities in schools  01-04-2025
Using the evaluation tools 10/2024-04/2025

 

WP5: Impact and dissemination/(JYU)

Preparing and publishing a toolkit including the pilot activities and the evaluation tools 01-04/2026
Presenting the data at scientific conferences with a focus on STEAM 05/2024-12/2025
Publishing 2 papers from the activities evaluation 06/2024-04/2026
Organizing workshops with teachers and teacher students where the activities will be presented 05/2024-4/2026

 

Project partners will be also responsible for the implementation of project outputs in their countries. This advantage of trust

assumes that the partners will receive more information and will be able to respond better to the corresponding countryspecific

needs of the project.

 

Each work package is led by a single partner, it will manage the cooperation with other partners by itself. Leaders will

provide a timetable and task plan for all partners and also manage the necessities at the local level. The leader will also

supervise the process and work progress of each partner. It will be also responsible for the synthesis of achievements and

actions undertaken by the rest of the partners in the particular intellectual output. All the aforementioned steps undertaken

by each organizer will be supervised by the main coordinator, that will also set specific output deadlines.